West Side Street Project

Schedule for Seeding

September 27th, 2011

The contractor Seeder Inc. is planning on starting the seeding in your neighborhood next week. Preparation of the yards may start earlier. Yards will be tilled, leveled, seeded and fertilized. If you have already established your yard by seeding or sod we will skip over those properties. After we have completed your yard it will be beneficial to keep the surface moist until the grass is established.

If you have any question please call.

Larry Schaller
Construction Engineeer
MKEC
796-2320

Seeding Eastborough

August 18th, 2011

John, we will ask the contractor to give us a schedule for seeding. We need to get word out to the residents so they can advise us if they do not want seed. People with Bermuda or sodding or other Landscape plans probably will not want seed, but some of these areas still may need final grading. We will need to have the contractor do final grading and loosening of the soil before they seed. Getting this done will take awhile. Earliest they could seed would be sometime next week, I would think.

We are working to have them clean the worst areas of dirt in gutters (area in front of Vickers both sides is probably the worst).

Larry Henry
MKEC Engineering Consultants, Inc
411 N. Webb Road
Wichita, Kansas 67206
(316) 684-9600
E-Mail: Lhenry@MKEC.com

Postal Service Home Delivery Resumes August 8th

August 4th, 2011

We have been informed that the Postal Service will begin delivery to the homes on the west side of Eastborough beginning Monday, August 8th.

Therefore, after the west side residents pick up their mail Saturday August 6th, please return your mail box keys to City Hall. If it is during regular office hours, there will be a basket on the table just inside the door. If it is after hours, please place your keys in a sealed envelope and drop them through the mail slot on the front door. Thank You.

Waste Connection Pickup Changed to August 1st

July 27th, 2011

Waste Connection has changed the pickup date from Friday, July 29th to Monday, August 1st, so as not to interfere with the street project.

Surface Asphalt Begins Wednesday, July 27th

July 26th, 2011

Kansas Paving will start laying the Surface Asphalt on Wednesday July 27th 2011 and July 28 2011, All Residents will be affected, on Wednesday Kansas Paving will start on East Norfolk and head East to Highland and then head North on N. Norfolk to E. Norfolk and head east to Hillcrest on E. Norfolk. On Thursday Kansas Paving will head South on Hillcrest to Douglas and then on Parkwood to Highland.

During this time Kansas Paving is requesting that all Residents call their Landscaping crews and reschedule them for another day and that all Resident on E Norfolk, Highland and N. Norfolk move their Vehicles on Wednesday and that all Residents on Hillcrest and Parkwood move their Vehicles on Thursday.

Thank you

Paul Albright
Kansas Paving
316-832-0828
paul@kansaspaving.com

Base Asphalt, Driveways, Backfill C&G, Sprinkler Heads

June 23rd, 2011

Attention Eastborough Resident:

Kansas Paving will open the Driveways on Hillcrest today and will need all residents on Hillcrest to park in the Driveways to allow for Construction to move up and down the streets, the cars that are parked in front of the driveways will need to be moved to allow Kansas Paving to open the Driveways.

Kansas Paving will begin fine grading the Rock base on Friday June 24th, 2011 and will need all Vehicles off the street.

Kansas Paving will lay the Base Asphalt on or around Tuesday June 28th, 2011 and on Wednesday June 29th,2011 and will need all residents in the area to park on N. Norfolk, E. Norfolk or Highland Ave.

Kansas Paving will continue Backfilling the C&G and Installing the sprinkler Heads.

Addresses affected for all the above notices are #1,2,3,4,5,6,7,8,9,10,11,12 & 21 Hillcrest, #12 & 13 E. Norfolk, # 2 & 4 Parkwood, # 1 Highland and 6004 E Douglas.

Thank you.

Paul Albright
Kansas Paving
316-832-0828
paul@kansaspaving.com

Weekly Update for the Week of June 13th to June 18th, 2011

June 10th, 2011

Attention Eastborough Resident:

Curb and Gutter

Kansas Paving will be setting the string Line for Curb and Gutter on or around Monday June 13th, 2011 and will grade the Driveways at the same time; all residents in the area will need to have their Vehicles out of the Driveways. (Except those with two Driveways)Kansas Paving will pour Curb & Gutter on or around Tuesday June 14th & Wednesday June 15th, 2011. Addresses affected in this area are # 32 E. Norfolk, # 21,12,11,10,9,8,7,6,5,4,3,2,1 Hillcrest Ave., # 2 & 4 Parkwood, # 1 Highland and 6004 E Douglas.

Driveways

Kansas Paving will be setting the forms for the Driveways on or around Thursday June 16th, 2011 and pour the Driveways on Friday June 17th, 2011.Addresses affected are the same as above.

Thank you.

Larry Schaller
Construction Engineeer
MKEC

Weekly Update for the Week of June 6th to June 10th, 2011

June 3rd, 2011

Attention Eastborough Resident:

Street and Driveway Removal

Kansas Paving will start Removal on Parkwood on or around June 6th, 2011. Addresses affected in this area are # 4&2 Hillcrest, # 2&4 Parkwood, # 1 Highland and 6004 E Douglas.

Asphalt Base

Kansas Paving plans on Laying Base Asphalt on N. Norfolk and on E. Norfolk on or around June 6th, 2011. Addresses affected in this area are #2 Parkwood,# 11,12,14,15,16,18,20 N. Norfolk, # 17,22,24,26,28,32 E. Norfolk and #12 Hillcrest.

Temporary Street Closures

N. Norfolk and E. Norfolk will be Temporary closed on June 6th, 2011 and reopened that evening. Kansas Paving will lay one side of the street at a time. Residents will need to have their vehicles off the street by 7:30 am Monday June 6th, 2011.

This schedule is subject to change due to weather or any unforeseen circumstances.

Thank you.

Paul Albright
Kansas Paving
316-832-0828
paul@kansaspaving.com

Sprinkler Heads

May 31st, 2011

Attention Eastborough Resident:

Kansas Paving has a Landscaping crew on site, they will need you to place all sprinkler heads on your front porch ASAP. They will also need to run your system in order to check for leaks in the lines, your help in expediting this process is greatly appreciated. If you choose to have your own landscaping crews install your lines and sprinklers heads please Email me. (paul@kansaspaving.com)

Thank you.

Paul Albright
Kansas Paving
316-832-0828
paul@kansaspaving.com

Eastborough Street Removal, Driveways, Base Asphalt

May 27th, 2011

Attention Eastborough Resident:

Street & Driveway Removal

Kansas Paving will start removal on N. Hillcrest Ave. on Tuesday May 31st, 2011 Addresses affected in this area are 12,11,10,9,8,7,6,5,4,3, N. Hillcrest Ave.

Driveways

Kansas Paving will pour Driveways on or around Wednesday June 1st, 2011. Addresses affected in this area are #2 Parkwood, # 11, 15, 17, 20, N. Norfolk, #24, 26 E Norfolk & # 12 N. Hillcrest Ave. Except those with two driveways Kansas Paving request that you move your Vehicle out of the drive until Wednesday June 8th ,2011.

Base Asphalt

Kansas Paving will lay Base Asphalt on or around Friday June 3rd, 2011 on N. Norfolk & E. Norfolk Rd. and will Temporary close E. Norfolk & N. Norfolk and reopen the streets that evening. Addresses affected in this area are #2 Parkwood, # 11,12,14,15,16,17,18,20,22,24 N. Norfolk and # 26, 28, 32 E. Norfolk Rd. and # 12 N. Hillcrest Ave.

Thank you.

Paul Albright
Kansas Paving
316-832-0828
paul@kansaspaving.com

Eastborough Street Removal, Asphalt Base, Curb & Gutter - Revisions

May 26th, 2011

Attention Eastborough Resident:

Removal

The removal process has been put on hold until Tuesday May 31st, 2011 to allow Kansas Paving to do clean up, backfill the curb, work on the sprinkler systems and grade the rock for Asphalt on E. Norfolk, N. Norfolk and the circle at Highland and N. Norfolk.

Curb & Gutter

The Curb & Gutter on N. Norfolk and on E. Norfolk is still scheduled for tomorrow Wednesday May 25th 2011.The Curb & Gutter has been moved to Thursday May 26th, 2011.

Asphalt Base

Kansas Paving will be laying the Asphalt Base on E. Norfolk and the circle at Highland & N. Norfolk on or around Friday May 27th 2011. Addresses affected in this area are # 8, 10, 3, & 5 E. Norfolk, # 1 & 4 Highland # 2 Parkwood, 5954 E. Douglas and #12 N. Norfolk. During this time E. Norfolk from Highland Dr. west to N. Norfolk will be temporary closed and reopened the same day.

Thank you.

Paul Albright
Kansas Paving
316-832-0828
paul@kansaspaving.com

Eastborough Street Removal, Asphalt Base, Curb & Gutter

May 25th, 2011

Attention Eastborough Resident:

Removal

The removal process has been put on hold until Thursday May 26th 2011 to allow Kansas Paving to do clean up, backfill the curb, work on the sprinkler systems and grade the rock for Asphalt on E. Norfolk, N. Norfolk and the circle at Highland and N. Norfolk.

Curb & Gutter

The Curb & Gutter on N. Norfolk and on E. Norfolk is still scheduled for tomorrow Wednesday May 25th 2011.

Asphalt Base

Kansas Paving will be laying the Asphalt Base on E. Norfolk and the circle at Highland & N. Norfolk on or around Friday May 27th 2011. Addresses affected in this area are # 8, 10, 3, & 5 E. Norfolk, # 1 & 4 Highland # 2 Parkwood, 5954 E. Douglas and #12 N. Norfolk. During this time E. Norfolk from Highland Dr. west to N. Norfolk will be temporary closed and reopened the same day.

Thank you.

Paul Albright
Kansas Paving
316-832-0828
paul@kansaspaving.com

Weekly Update for the Week of May 23rd to May 28th

May 20th, 2011

Attention Eastborough Residents:

Street Removal

Kansas Paving is removing the Asphalt Street, Driveways and Mail Boxes on Hillcrest from E. Norfolk Rd. to Parkwood. Addresses in this area that will be affected are # 12,11,10,9,8,7,6,5,4,3,2 & 1 N. Hillcrest Ave. Kansas Paving will start removal on or around Thursday May 26th , 2011 on Parkwood from Hillcrest to N. Norfolk Dr .Addresses in this area that will be affected are # 4 Hillcrest, # 2 & 4 Parkwood, #1 N. Highland and 6004 E. Douglas.

Curb & Gutter

Kansas Paving will pour the Curb & Gutter on or around Wednesday May 25th, 2011.The Residents in this area will need to move their Vehicles out the Driveways on Wednesday May 25th . Addresses in this area that will be affected are # 2 Parkwood, # 11, 15 & 17 N. Norfolk Dr, and # 12 N. Hillcrest Ave.

Driveways

The Residents at Addresses # 5,8,10, 12, 14, 16 Norfolk, # 4 & 1 Highland and # 5954 E Douglas will be able to use their Driveways on Monday May 23rd, 2011.

Kansas Paving will pour the Driveways on N. Norfolk and on E. Norfolk on Monday May 23rd ,2011 weather permitting. Addresses affected are 18,20,22,24,26,28 E.& N Norfolk, these Driveways will be out of cure and ready for use on or around Monday 30th ,2011.

Street Closure

The intersection at 2nd and Woodlawn is open. All other intersections are open.

Thank you.

Paul Albright
Kansas Paving
316-832-0828
paul@kansaspaving.com

Eastborough Street Removal and Road Closures,Driveways,Curb & Gutter

May 16th, 2011

Attention Eastborough Residents:

Removal

Kansas Paving will continue removal on E. Norfolk Dr. and will reach the circle by the midday on Monday May 16th, 2011, at this time we will began the removal of the circle on the North side and on the west side of the circle. Addresses affected in this area are # 28 and 32 Norfolk, # 12, 11, 21, Hillcrest.

On Tuesday May 17th, 2011 Kansas Paving will have a crew removing the North side of the Circle at Hillcrest and Parkwood and will need to close Parkwood for one Day at Parkwood and Hillcrest. The intersection at Hillcrest and Douglas will remain open, 2nd street and Woodlawn will remain open and E. Norfolk Dr. will be open. Addresses affected in this area are # 1,2,3,4, N. Hillcrest Ave.

On Wednesday May 18th, 2011 Kansas Paving will close the intersection on 2nd Street and Woodlawn and continue removal from the North side of the circle to Woodlawn. Addresses affected in this area are # 12, 11, 21 N. Hillcrest Ave. and # 32 E. Norfolk.

On or around Thursday May 19th, 2011 Kansas Paving will start the removal on N. Hillcrest Ave. On the North end of N. Hillcrest Ave. Addresses affected in this area are # 32, 12, 11, 10, 9, 8, 7, 6.5.4, 3, 1 N. Hillcrest. During this time 2nd Street will be open to Residents on E. Norfolk Dr. All other entrances will be open.

Driveways

Kansas Paving is pouring the driveways on Monday May 16th,2011 on E. Norfolk Dr, Highland and N. Norfolk Dr. The Residents in this area will be able to drive on their Driveways on Monday May23, 2011.

Curb & Gutter

Kansas Paving will be setting string line for Curb & Gutter on N. Norfolk Dr. on or around May 17th, 2011 and pouring the Curb and Gutter on Wednesday May 18th, 2011. During this time Residents will need to move their Vehicles out of the Drives .Addresses affected in this area are # 16,18,20,22,24,26,28 E. Norfolk and N. Norfolk Dr.

Curb and Gutter Plan Clarification

May 12th, 2011

In an effort to clarify the plan for curb and gutter work on the west side of the neighborhood, I have met with John Johnson and the contractor to discuss the effects of constructing full 6 inch curb along some of the areas on West Norfolk, in the deepest cut areas.

The impact of using 6 inch curbing would reduce some of the steepness of the grading from the construction limits to the new curb. While this option is feasible, it would create discontinuity in the curb heights in the loop streets. We therefore will proceed with the original plan and provide roll curb throughout the loop.

The steep slopes are related to conditions we placed in the specifications to protect any trees and landscaping lying more than 5 ft behind the new curb. As I noted in our public meetings, this limitation on grading would create some steep areas to the new curb. However it serves the purpose of protecting trees from surface grading around the trunks. Protection of the trees has been a top priority for the neighborhood and the designers.

In areas where steepness can be helped by grading farther back than 5 ft., we plan to individually contact the property owners to determine their preference about grading limits. This will allow a mutually agreed to grading limit which will be most appropriate for the property. If the owners wish to allow grading farther back to reduce the slope, it will be done. Our intent is to provide the needed protection of trees and landscaped areas, and work with homeowners to create the best overall slopes in non-landscaped areas.

One area where full 6-inch curbing is most beneficial is West Norfolk, west of the loop street. This location has the most significant slopes, which can be better maintained through using the higher curb. This segment of street will be paved with 6-inch curbing. But the curbing will be transitioned to roll-type curb before it enters the loop streets.

This plan will allow the continuity desired for the neighborhood, and provide the coordination with each citizen as to the desired grading limits to match their property elevation.

Larry Schaller, MKEC's Construction Engineer will be in the neighborhood and in contact with neighbors once the curb is poured. Thank you for your assistance in coordinating this with Larry.

Larry Henry
MKEC Engineering Consultants, Inc
411 N. Webb Road
Wichita, Kansas 67206
(316) 684-9600
E-Mail: Lhenry@MKEC.com

EASTBOROUGH STREET REMOVAL, CURB & GUTTER, DRIVEWAYS

May 11th, 2011

Attention Eastborough Residents:

Kansas Paving has moved a Crew in for Removal on Hillcrest Ave.; they will start removal on Hillcrest Ave. and Douglas and continue up to the Circle. The Address's affected by this are # 1 & # 2 Hillcrest Ave. The entrance at Hillcrest & Douglas will be temporary closed during this time.

Kansas Paving is setting string line for the Curb Machine today and will pour the Curb & Gutter on Thursday May 12th 2011 on E. Norfolk, N. Norfolk & Highland Streets, including the Median at Highland & Norfolk. Address's affected in this area are # 3,5,4,8,10,12,E. Norfolk, # 4 & 1 Highland and # 14,16,18,N. Norfolk Dr. During this time Kansas Paving is requesting that you move your Vehicles that you Drive at of the Driveway . Soon after we pour the Curb & Gutter Kansas Paving will start setting forms for the Driveways and pour the Driveways back as soon as possible. There is a 7 day cure time on Concrete Driveways, after the 7 days you will be allowed to use your Driveways.

Thank you

Paul Albright
Kansas Paving
316-832-0828
paul@kansaspaving.com

Requested Change Order on Curbing

May 11th, 2011

MKEC has requested a change order on the curbing. This affects 3,5,8,10,11,12,14,15,16,17,18,20,24 Norfork, a portion of 4 Highland and a portion of 2 Parkwood. As you probably have noticed, there is a significant change in elevation between the road bed and the lawns. This portion of the streets had to be graded deeper to achieve the proper drainage contours. MKEC is concerned that with the constraints we have made to grade only five feet back of the curb, the drop off will be severe. While there will be an additional 5 inches of asphalt poured on top of the road bed, there will still be a difference in elevation. Therefore, MKEC wants to put in traditional curbs at these areas as opposed to rolling curbs which are in the original design. Close consideration of this change request leads to the conclusion a normal curb in this area certainly makes sense. I know that we have consistently stated we would be using rolling curbs for the entire project, but we now realize that our accommodation to limit the grading to five feet instead of ten feet has created this dilemma. During the landscaping phase of this project, the contractor will be meeting with residents to discuss landscaping back beyond five feet where it won't affect any trees to help in alleviating this problem.

Street Map for Change Order Request

We will keep you updated on the construction process.

John

John W. Johnson
Morris,Laing,Evans,Brock & Kennedy
300 N. Mead
Suite 200
Wichita, Ks 67202
316 262 2671
316 262 5991 FAX
jjohnson@morrislaing.com

EASTBOROUGH STREET REMOVAL, CURB & GUTTER, DRIVEWAYS

May 10th, 2011

Attention Eastborough Residents:

Kansas Paving will continue the street removal on N. Norfolk Dr. up to the circle at E. Norfolk & N. Norfolk ,and then move to the Northwest corner and start removal on or around May 10th, 2011 at Address # 22 Norfolk and remove up to the circle. The week of May 16th Kansas Paving will remove from the circle and head east on E. Norfolk Dr. Addresses that will be affected are 16 ,18,20,22,15,17,24 N. Norfolk Dr. and 26,28,32,E Norfolk Dr. and # 12 Hillcrest

Kansas Paving will have a crew on site to set string line for the Curb & Gutter on or around Wednesday May 11th, 2011 on the North and South sides of E. Norfolk Dr. and on the East & West sides of Highland, and will pour the Curb & Gutter on or around Thursday May 12th, 2011, at this time you will need to move your Vehicles at of the Driveways , Addresses that will be affected are # 3, 5, 8, 10, & 12 N. Norfolk Dr., #4 Highland and 5954 E Douglas.

Kansas Paving will start setting up the Driveways on or around Friday May 13th, 2011 and start pouring the Driveways on or around Monday May 16th, 2011. During this time we ask that you please park in the street away from the Driveways. The Driveways will be out of cure on or around Monday May 23rd, 2011 .Addresses affected are the same as the Curb & Gutter.

Thank for your patience

Paul Albright
Kansas Paving
316-832-0828
paul@kansaspaving.com

STREET REMOVAL ON HIGHLAND AND THE SOUTH SIDE OF THE CIRCLE @ PARKWOOD AND HIGHLAND

May 3rd, 2011

Attention Eastborough Residents:

May 3, 2011 Kansas Paving will continue removal on Highland and the intersection at Highland, Parkwood & Norfolk and then move North on N Norfolk Dr.

May 3, 2011 Parkwood will be temporary closed to allow Kansas Paving to finish removal of the pavement in the south half of the circle.

On or around May 5, 2011 the South half of the circle at Parkwood and Highland and the intersection at Highland and Douglas will be opened to allow Kansas Paving to close the North half of the Circle. We will then close N. Norfolk Dr. to thru Traffic on or around May 5, 2011.

The intersection of Hillcrest Ave. and Woodlawn is now opened.(May 3, 2011)

MAIL BOXES, STREET & DRIVEWAY REMOVAL ,TEMPORARY STREET CLOSURES

April 29th, 2011

Attention Eastborough Residents:

Kansas Paving will be removing the Mail boxes as we move through the area ,if you would like to save your Mail box please remove it ,if you have a Brick or Stone Mail Box and would like to save the Brick or Stone please send an Email to paul@kansaspaving.com with your Address .

Kansas Paving will continue the removal process through the intersection of E Norfolk Dr., N Norfolk Dr., Highland and E Parkwood on Friday April 29th,2011 we will remove the North half of the intersection and move North on N Norfolk Dr. Addresses that will be affected in this area are #4,12,14,16,18,20,22,17,15,11,N. Norfolk Dr. , #2 E. Parkwood Dr.and E. Norfolk Dr.#24,26,.

N. Norfolk Dr. will be Temporary closed from the North side of E. Parkwood Dr.. Residents will be able to get to their Driveways from the North end of N Norfolk Dr. the road will be reopened at Night.

Thank you

Paul Albright
Kansas Paving
(316)832-0828
paul@kansaspaving.com

MAIL DELIVERY CHANGES

April 26th, 2011

The mail delivery issue has been a key element in the west side road construction project. Initially we were going to try and install a bank of temporary boxes on the west side. The Postal Service had been contacted last year and was studying the issue. During discussions with MKEC, we decided to incorporate into the construction contract the requirement to leave one lane open for access to homes and mail delivery. However, the Postal Service, after studying that plan made the determination it was not feasible for their delivery procedures. With that in mind, the contractor proposed abandoning the one lane plan and proposed excavating both lanes at once and laying down crushed concrete for driver access. While this method would close off two to four residences from mail delivery at any given time, it was perceived as a viable procedure. I discussed it with the Postal Service and it was felt it was workable. That was the plan presented to the citizens at the informational meeting. However, as that plan has been studied, it became apparent it was burdened with its own problems. There are going to be big differences in elevation from the road bed to the mail boxes and the temporary boxes were going to be set back a greater distance than they are now. Adding to the fact there will be a curing concrete curb in front of the mail boxes, it became apparent this was not a workable solution. There would be too many separate instances where residents would not get their mail that the benefits of home delivery would be overshadowed. The Postal Service has temporary mail boxes and it has agreed to install them at the turnaround between Douglas and Huntington. There is an asphalt inset that is present and held a mail drop off box years ago. Furthermore, there is a light right behind where the boxes will be positioned. After meeting with the Postal Service at the site in question, it was determined this was the best location. (We tried to find a place on the west side that would work and after looking at all the options, the current site was deemed the most advantageous.)

The boxes are being installed this morning. The Postal Service has dropped off keys with instructions at City Hall. Mail service will begin Thursday. If a parcel is too big for your box, a key will be placed in your box to access the larger box in your bank of boxes. That key must be used to access the larger box. Once inserted and opened, only the mail man will be able to remove it. If there is not enough room in the larger box, the parcel(s) will be taken to City Hall with a note left in your regular box advising of the action taken.

There has been a concern over the fact that once we go to this system, the Postal Service will not return to home delivery once construction is completed. This concern was alleviated several months ago by the Postal Service and it was communicated to the residents. The Postal Service has again assured me this bank of boxes is only temporary. In fact, the boxes are considered temporary and are used at other locations when needed. We have asked the Postal Service to provide the residents with instructions on the installment of new mail boxes after construction is completed and it has agreed.

I know this is a change in plans, but it has been made only after a lot of study and discussion.

John W. Johnson
john.johnson@eastborough-ks.gov

KANSAS PAVING STARTS REMOVAL APRIL 27

April 26th, 2011

Kansas Paving will start removal from East Norfolk Dr. to North Norfolk Dr. on or around Wednesday April 27, 2011. Address's that will be affected are 3,4,5,8,10,& 12 East Norfolk Dr.

WB Carter will complete the Storm Water sewer on or around Wednesday April 27, 2011, at which time Douglas and Hillcrest will be open.

WB Carter will move to 2nd Street on or around Wednesday April 27, 2011 and begin the Storm Water Sewer in that area, at which time 2ND Street Woodlawn intersection will be closed. Address's that will be affected are 21 North Hillcrest Ave. & 32 East Norfolk Dr.

MAIL SERVICE CONCERNS

April 20th, 2011

I am aware of concerns from our residents about mail service on the west side. We have been in discussions for several months with the Postal Service pertaining to this issue. We have done our best to try and keep roadside mail delivery to each residence. In fact we thought the issue had been decided after we were advised by the Postal Service delivery could be made over the temporary surface put down by the contractor. However, after studying the issue with MKEC, we have come to the conclusion residential delivery will not only cause problems for the postman, but also to citizens in trying to access their mailboxes.

After meeting with Postal Officials, we have decided to place a temporary bank of mailboxes at the Hampton turnaround between Douglas and Huntington. In the past, there was a Postal drop off box at that location. The boxes will have locks and citizens will be issued keys for their respective boxes. A notice will be sent when the keys may be picked up at City Hall. The new bank of mailboxes will be installed within the next week and we will advise you when mail delivery is switched.

After the construction is complete, roadside mail delivery will be resumed, using new mailboxes installed by the contractor. Of course, some residents will want to construct new custom mailboxes after the street construction. This should be delayed until the contractor's work is complete to avoid conflicts with those operations.

We understand this option for mail delivery is an inconvenience, but it is the best way to provide safe and secure mail service during this temporary period. Thank you for your continued patience.

John W. Johnson
john.johnson@eastborough-ks.gov

OPPORTUNITY FOR ADDITIONAL WORK BY KANSAS PAVING

April 20th, 2011

Kansas Paving would like to let residents know that additional work can be done beyond the construction limits if desired. If interested, please send your name, phone number, and address to Barbara Kratzer (barbara.kratzer@eastborough-ks.gov), and she will forward the residents information to us.

Kansas Paving will have an estimator get in contact with any interested residents before the removals get started.

Chris Wolken
Kansas Paving
316-832-0828
chris@kansaspaving.com

MAIL SERVICE CONCERNS

April 20th, 2011

I am aware of concerns from our residents about mail service on the west side. We have been in discussions for several months with the Postal Service pertaining to this issue. We have done our best to try and keep roadside mail delivery to each residence. In fact we thought the issue had been decided after we were advised by the Postal Service delivery could be made over the temporary surface put down by the contractor. However, after studying the issue with MKEC, we have come to the conclusion residential delivery will not only cause problems for the postman, but also to citizens in trying to access their mailboxes.

After meeting with Postal Officials, we have decided to place a temporary bank of mailboxes at the Hampton turnaround between Douglas and Huntington. In the past, there was a Postal drop off box at that location. The boxes will have locks and citizens will be issued keys for their respective boxes. A notice will be sent when the keys may be picked up at City Hall. The new bank of mailboxes will be installed within the next week and we will advise you when mail delivery is switched.

After the construction is complete, roadside mail delivery will be resumed, using new mailboxes installed by the contractor. Of course, some residents will want to construct new custom mailboxes after the street construction. This should be delayed until the contractor's work is complete to avoid conflicts with those operations.

We understand this option for mail delivery is an inconvenience, but it is the best way to provide safe and secure mail service during this temporary period. Thank you for your continued patience.

John W. Johnson

NEWS LETTER FOR WEST EASTBOROUGH RESIDENTS

April 18th, 2011

Kansas Paving is working on a system to have regular notices sent by e-mail or by flyer to all the residence affected by the street construction. These emails will try to inform you about what is happening and when it might affect your area of the project.

Right now, the contractor is getting the project surveyed and marked out with wood stakes driven into the ground. This will give the new alignment and elevations for the new curb. The stakes (marked with red flags) are 5 ft behind the proposed new curb.

Some protective fencing is being installed. The protective fencing is also being placed at the 5 ft line to protect the trees and landscaping behind it. This should give the citizens an idea where the new curb will be, and what things will be impacted by the construction. If anyone has things out in the construction area they would like to save, they should make those arrangements as soon as possible. The contractor will remove things in the construction area, and citizens can contact them if some of these things need to be salvaged for the owners.

There are also some red flags or markings on the driveways and sidewalks showing the limits of the driveway removal limits. Contact the contractor if you have any questions of these limits of removal.

Access will be limited at times and will change during the phasing of this construction. Contractor will be sending out notices of these traffic changes.

The contractor shall maintain access to all individual mailboxes. Existing mail boxes that are in the construction area (area that is 5ft behind curb) will have to be removed. Temporary mailboxes will be installed prior to the removal of the existing ones. Permanent mailboxes will be installed at the end of construction for each residence.

Larry D. Henry
MKEC Engineering Consultants, Inc
411 N. Webb Road
Wichita, Kansas 67206
(316) 684-9600

ATTENTION EASTBOROUGH RESIDENTS

April 15th, 2011

Beginning Monday, April 18, W.B. Carter Construction Co. will begin work on the storm water sewer located at Douglas and Hillcrest Avenue. The contractor will begin at the existing storm water inlet on Douglas, and install pipe to the north along the west side of Hillcrest, ending at the north side of Parkwood Drive. This work will take approximately 2 weeks.

Kansas paving will close N. Hillcrest Ave. from Douglas to the first driveway on the east side of N. Hillcrest. Addresses in the area that will be affected are #1 N. Hillcrest and #2 N. Hillcrest Ave.

Residents in the area will be able to use the 2nd Street and Woodlawn entrance, the Highland entrance at Douglas, and the West Norfolk entrance during this time.

Thank you for your patience

Paul Albright
Kansas Paving
(316)832-0828